The city was awarded a $29,600,000.00 Grant through the Florida Department of Environmental Protection to replace & re-purpose existing Wastewater Treatment Facility with a new advanced Treatment WWTF.
- Bids were opened and read publicly and aloud on February 4, 2025 at 2:00pm. (Link to Bid Opening Sheet: DEP WG088 Bid Opening Sheet 1 2 4 2025 2pm)
- Bid Advertisement was published in Union County Times on January 2, 2025.
- In Phase 3-5 of Project
- Amendment number 1 to Agreement WG088 updating the end date to December 31, 2026
- Engineer Service Agreement executed December 2022 with Mittauer & Associates and the City of Lake Butler.
- Grant Agreement Executed October 2022 with State of Florida, Florida Department of Environmental Protection
- Preliminary Engineering Review completed June 3, 2021
- Application submitted January 2021