Wastewater Treatment Facility – Grant #WG088

The city was awarded a $29,600,000.00 Grant through the Florida Department of Environmental Protection to replace & re-purpose existing Wastewater Treatment Facility with a new advanced Treatment WWTF.

  • Bids were opened and read publicly and aloud on February 4, 2025 at 2:00pm. (Link to Bid Opening Sheet: DEP WG088 Bid Opening Sheet 1 2 4 2025 2pm)
  • Bid Advertisement was published in Union County Times on January 2, 2025. 
  • In Phase 3-5 of Project
  • Amendment number 1 to Agreement WG088 updating the end date to December 31, 2026
  • Engineer Service Agreement executed December 2022 with Mittauer & Associates and the City of Lake Butler.
  • Grant Agreement Executed October 2022 with State of Florida, Florida Department of Environmental Protection
  • Preliminary Engineering Review completed June 3, 2021
  • Application submitted January 2021