The city was awarded a $875,000.00 Grant through Florida Department of Environmental Protection #LPA0314 to replace the drinking water tank.
- Next Update to go here
- Payment Request for $10,000 was submitted February 16, 2023, to the Department of Environmental Planning
- Engineer Service Agreement executed January 17, 2023, with Mittauer & Associates
- Grant Agreement LPA0314 was fully Executed on July 25, 2022
- Amendment #1 to Agreement LPA0314 to extend the expiration date of the Grant
- Grant Agreement LPA0314 was fully Executed on July 25, 2022
- Inspection was completed of the Ground Storage Tank May 11, 2020